Final Tasks and Conclusion

Topic

Final Tasks and Conclusion

If the relay was programmed correctly, it has been creating event logs, oscillography records, and metering information. (You check to make sure these functions are all working correctly when you test your relays… right?)  This video shows you how you can clean up after yourself.

More importantly, a final meter test should be performed on ALL relays after they have been energized and some load flows through the relay to make sure that all of the connections are correct instead of relying on simulations.

Click “Mark Complete” below after watching the video so you can keep track of your progress.

3 Comments
Collapse Comments

Leave a Comment